Yard House

Boston, MA


Type of project: Fit-out
Duration of Project: 24 weeks
Square footage: 10,000 sf
Partners: MBH Architects

Noteworthy: The site was located in the Ground Water Overlay District of Boston, necessitating extensive due diligence and planning to ensure proper measures were taken during construction. The schedule was accelerated to ensure completion by Fenway Park’s 100th anniversary celebration. Shawmut has completed 16 locations nationwide.